July 2020 Update

July 2020 saw the rapid demolition of the aged Nativity parking lot. Within 2 days the entire asphalt surface was scraped clean and trucked away. Then the "San Luis clay" was removed to make room for 9 inches of new base that will be compacted and tested for compliance to specifications. Additionally the lateral sewer line from the north garden area across the parking lot was replaced and reconnected to the street sewer and inspected by the City of SLO. Things are moving fast now, but we still are in need of close to $1 million to complete all of our plans for the 3 priorities of the Raising the Star project.

$2.9 Million
As Of:
Jul 10, 2020 7:26 PM
25% Left To Reach Our Goal.